Text
1. The Defendant’s KRW 500,000,000 and the Plaintiff’s annual rate of 5% from May 1, 2017 to May 4, 2018.
Reasons
1. The description of the claim is as shown in the annexed sheet of claim.
2. Judgment by public notice of applicable provisions of Acts (Article 208 (3) 3 of the Civil Procedure Act);
3. The ground for partial dismissal is that the Plaintiff sought payment of damages for delay from April 30, 2017, which is the date of repayment, for KRW 500 million, for which the Defendant is liable to pay to the Plaintiff pursuant to the loan certificate (Evidence A7). However, it is not from the date when the due date comes to the due date, but from the following day since the obligor is liable for delay for the obligation with the due date, such as the obligation to pay the due date. Therefore, the part on the claim for damages for delay from April 30, 2017 for KRW 50