(영문) 서울남부지방법원 2018.05.24 2018가단202518
보증채무금
Text

1. The defendant shall pay to the plaintiff KRW 254,691,657 and KRW 238,224,087 among them, from December 14, 2017 to the date of full payment.

Reasons

Attached Form

The entry does not clearly conflict between the parties.

(However, “creditor” and “debtor” are co-suretiess of a limited partnership company B. Therefore, the Defendant is obligated to pay damages for delay calculated at the rate of 25% per annum, which is the overdue interest rate, from December 14, 2017, to the date of full payment, to the date of full payment, to the date of full payment, with the maximum amount of KRW 49.2 million, to the Plaintiff, a creditor, as a joint and several surety of the debtor limited partnership company B. Therefore, the Defendant is obligated to pay damages for delay calculated at the rate of 25% per annum, which is the overdue interest rate, within the maximum of KRW 49.2 million per annum to the Plaintiff, a creditor.

Thus, the plaintiff's claim of this case is legitimate, and it is decided to accept it.

arrow