1. The Defendant’s KRW 1,218,191,729 among the Plaintiff and KRW 1,009,547,797 among the Plaintiff, shall be KRW 58,273,609.

Reasons

1. Basic facts

A. The Plaintiff is an autonomous management body organized by the occupants to manage the A Apartment Complex B in Eunpyeong-gu Seoul Metropolitan Government (hereinafter “instant apartment complex”) 16 and 947 households (general 606 households, public lease 341 households). The Defendant is a project proprietor who constructed and sold the instant apartment and the Intervenor’s Intervenor is the instant apartment construction contractor.

B. On January 12, 2009, the apartment of this case had undergone a pre-use inspection on the apartment of this case. The defendant joining the defendant constructed the apartment of this case on the construction of the new apartment of this case, or changed the part to be constructed according to the design drawing differently from the defective construction or design drawing and constructed the apartment of this case, thereby causing trouble in the function, aesthetic or safety of the apartment of this case, thereby causing trouble to the function, aesthetic or safety of the apartment of this case. 2) Accordingly, although the plaintiff requested repair of defects on several occasions at the request of the tenant or sectional owner, some repair work was performed on the part of the common area and the section for exclusive use of the apartment of this case (However, the part for exclusive use by the public rental household was not conducted with defect appraisal).

1. Totalization table by defect list of the section for common use and attached Table;

2. Each defect in the summary sheet by section of exclusive ownership (hereinafter “instant defect”) remains, and the repair cost description to repair the defect based on the partial design is as follows:

After the pre-use inspection on the model of defect repair expenses, the 106,333,282,282,217,55,848,47,404, 787, 982, 205,679, 679, 679, 146, 871, 106, 333, 282,282, 217,536,8454, 928, 914, 011, 715, 912, 934, 10,262,52, 1965, 115, 13265, 37, 3729, 375, 1468, 2975, 297, 2864, 297, 257, 2987, 2965, 287, 2975