(영문) 수원지방법원 안산지원 2018.12.05 2018가단60673
약정금
Text

1. The Plaintiff, Defendant B, and Defendant C, jointly and severally with Defendant B, KRW 30,00,000, and each of the above amounts.

Reasons

On June 14, 2013, Defendant B requested the Plaintiff to discount the 30 million won fake bill and then used the discounted amount at will without returning it to the Plaintiff.

Afterward, on July 30, 2014, Defendant B agreed to pay to the Plaintiff in installments the amount of KRW 45 million plus KRW 12.6 million and KRW 2.4 million until August 30, 2014 and KRW 35 million until September 30, 2014, with the joint and several guarantee of Defendant C.

【In light of the fact that there is no dispute, Gap 1-3 evidence, and the purport of the entire pleadings, the plaintiff is obligated to pay damages for delay calculated at the rate of 15% per annum as prescribed by the Act on Special Cases Concerning the Promotion, etc. of Legal Proceedings from July 13, 2018 to the date of delivery of the copy of the complaint to the defendants, as to the above amount as to the amount as KRW 30,000,000, and the amount as to each of the above amounts as claimed by the plaintiff, jointly and severally with the defendant Eul, with the exception of KRW 5,80,000,000,000, excluding the agreed amount of KRW 45,000,000,000, which is paid by the plaintiff.

The plaintiff's claim against the defendants is justified, and it is so decided as per Disposition.