(영문) 광주지방법원순천지원 2015.09.10 2015가단8760
대여금반환
Text

1. The Defendant’s KRW 38,200,000 for the Plaintiff and KRW 5% from March 1, 2012 to July 8, 2015, and the next day.

Reasons

1. On December 11, 201, the Plaintiff indicated the claim and lent the amount of KRW 38,200,000 to the Defendant as of February 29, 2012 on the due date.

However, even though the due date for the above loan was expired, the defendant urged several times due to the failure to perform his obligations. However, the defendant did not comply with this demand and did not pay it in full only once a day after the next day. Thus, the plaintiff sought payment of the loan principal to the defendant as KRW 38,200,000 and damages for delay as to the above money.

2. Articles 208(3)1 and 257 of the Civil Procedure Act: A judgment without holding any pleadings;