(영문) 광주지방법원목포지원 2014.11.20 2013가합2158
동산인도
Text

1. Of the instant lawsuit, the part against Defendant branch Es. Construction Co., Ltd is dismissed.

2. The defendant Taechicing industry.

Reasons

1. Basic facts

A. On April 21, 2011, the Plaintiff entered into a lease agreement on the shit file (SHET FILE) (hereinafter “instant lease agreement”) with Defendant Thai River Industry Co., Ltd. (hereinafter “Defendant Thai River Industry”).

The main contents of the instant lease agreement are as follows.

Lease goods and their quantities: the price of leased goods at the construction site (referring to the site of construction in the public sewerage treatment plant (referring to high 1,100 tons), the construction site of the public sewerage treatment plant in the Myanmar, the construction site of the public sewerage treatment plant in the public road in the public road in the public road in the public road in the public road in the public road in the public road in the public road in the public road in the public road in the public road in the public road in the public road in the public road in the public road in the public road in the public road in the public road in the public road in the public road in the public road in the public road in the public road in the public road in the public road in the public road in the public road in the public road in the public road in the public road in the public road in the public road in the public road in the public road in the public road in the public road in the public road in the public road in the public road in the public road in the public road in the public road in the public road in the public road in the public road: 2,000,00 won: three months thereafter.

B. On April 21, 201, the Plaintiff entered into a contract to provide the Plaintiff with 3,000 foot files, the ownership of the Defendant Thai River Industry, as a collateral for transfer, to secure the rental fee liability under the instant lease agreement with the Defendant Thai River Industries.

C. On November 9, 2011, Defendant SP Construction Co., Ltd (hereinafter “Defendant SP construction”) entered into a contract with Defendant SP (hereinafter “instant sales contract”) to purchase 3,711,937 km files from Defendant SPG during the period from November 1, 201 to December 31, 2012 (hereinafter “instant sales contract”). Pursuant to the instant sales contract, Defendant SPG paid KRW 3,834,627,850 on December 1, 201, totaling KRW 864,364,30,230,98,979,969,97,98,000 among the Defendant SPG industries.

On August 1, 2013, Defendant S. Construction changed the term of delivery of the instant sales contract between Defendant Thai C&D to September 30, 2013, and Defendant C&D supplied until that time by September 30, 2013.