Text
1. The plaintiff's claim is dismissed.
2. The costs of lawsuit shall be borne by the Plaintiff.
Reasons
1. Basic facts
A. On June 20, 2006, in order to jointly develop the land of this case into the “an aggregate agricultural and industrial cooperative complex” by 11 sectional owners [a] of the 11st sectional owners [a] co-owner of the land of this case (hereinafter referred to as the “instant land by combining the land of this case”) including Ansan-si and 9 lots (hereinafter referred to as the “instant land”), the Plaintiff Company was established on June 20, 2006, and the development costs are shared according to the ratio of the area of land owned by each owner.
B. On December 28, 2009, the Plaintiff contracted the construction of factory site for the instant land in KRW 4.8 billion and around December 2012, 2012, the Plaintiff demanded the F to supplement the construction of access roads and the installation of non-point pollution disposal facilities, etc., even though, around October 2013, the Plaintiff entered the end of all the construction works on the access roads to P Co., Ltd., and undergo a completion inspection on development activities under the name of the owner and the sectional owners.
C. On March 10, 2015, sectional owners sought an explanation of the progress of the instant land development activities, etc. from the Plaintiff, and resolved to share the cost associated with the reconstruction of access roads and the completion of development activities. The Plaintiff is seeking to repair access roads to the instant land from April 10, 2015 to July 10, 2016, such as the improvement of access roads signal such as the installation of non-point pollution disposal facilities, etc., improvement of urban planning roads, construction of underground facilities, and change of status unit plans.
After the Supplementary Construction (hereinafter “instant Supplementary Construction”) was conducted on July 27, 2016, the instant Supplementary Construction was completed after July 27, 2016. As to some of the instant Supplementary Construction (hereinafter “instant Construction”), five copies of the contract signed between the Plaintiff and the R that operates Qu were as follows:
(A) The contract formed through this is referred to as the “instant contract.” ① On July 20, 2015, the first phase of road construction works.