1. The defendant's KRW 18,659,930 per annum against each of the plaintiffs and 5% per annum from June 4, 2019 to June 23, 2020.
Reasons
1. Details, etc. of ruling;
(a) A project approval and public notice - A project name: A redevelopment project (C Housing Redevelopment and Improvement Project (Ij) - A project approval: A public notice of project approval on July 19, 2006; D public notice of Busan District on September 28, 201; B public notice of Busan District on September 28, 201; F public notice of Busan District on December 7, 201; G public notice of Busan District on August 22, 2018; Defendant:
B. Adjudication on expropriation by the Regional Land Tribunal of Busan Metropolitan City on April 8, 2019 (hereinafter in this case’s adjudication on expropriation): Each land indicated as “subject matter of expropriation” in the attached Table (hereinafter in this case’s land) in the attached Table (hereinafter “subject matter of expropriation”), and the parcel number shall be specified only when classification is necessary. Although any building or other object on the ground was subject to adjudication, no dispute exists on either party, and excluding the judgment in this case’s decision on expropriation): The starting date of expropriation: Compensation for losses June 3, 2019 - In the attached Table, the “subject matter of expropriation” is indicated.
C. The Central Land Tribunal’s ruling on objection on November 21, 2019 (hereinafter in this case’s ruling on objection) - Compensation for losses: The same shall apply to the statement on the “amount of compensation for objection” in the attached Table.
The result of the commission of appraisal to certified public appraiser H of this Court (hereinafter referred to as the ¡°the result of appraisal by the court¡±) - Contents of appraisal: The appraised amount of each of the lands of this case shall be as follows:
The fact that each of the plaintiffs 1/2 shares 691,163,000 1,163,130,436,000 each of the plaintiffs 1/2 shares 1/2 shares of 1/300 of 1,691,163,000,436,000 1/2 shares in Busan-gu Busan-gu J. 2001, J. 691,163,000,247,000 1/2 shares [based on recognition], each of the statements in subparagraphs 1 through 4, the appraisal statement in subparagraphs 1 through 4, the result of the appraisal commission for appraiser H by this court,
2. The assertion and judgment
A. The Plaintiff’s assertion that the amount of compensation for the instant case is lower than the price of the land subject to expropriation, thereby falling short of the reasonable amount of compensation. Therefore, the Defendant is subject to the court’s appraisal and the instant ruling of compensation.