1. The Plaintiff:
A. Defendant A’s KRW 41,800,000 and for this, KRW 5% per annum from August 15, 2014 to May 7, 2015.
Reasons
1. Basic facts
A. Korea Asset Trust Co., Ltd. (hereinafter “Korea Asset Trust”) uses the term “bable block” in the same sense as in the G apartment (a complex G apartment supply contract in the same sense as in the G apartment complex G apartment contract located in Yongsan-gu, Yongsan-gu. 79 households, 2 complex 237 households, total 316 households, and hereinafter “instant apartment”) from Epid Co., Ltd. (hereinafter “Epid”). The Plaintiff is a company that built the instant apartment.
B. 1) The Defendants are entitled to each household unit of the Korea Asset Trust and the instant apartment complex two complexes as follows (hereinafter “each of the instant supply contracts”).
The contractor's contract date and the contract deposit amount A. A., June 26, 2009, KRW 30 million,000,000 won for Defendant B, July 28, 2008, KRW 20,000,000 won for Defendant C, June 70, 2009, KRW 30,000,000 won for 380,000,000 won for 488,000,000 won for July 14, 2008, KRW 18,000,000 won for Defendant D. E, July 14, 2008, KRW 18,000,000 for each of the following major contents of the supply contract as follows:
(A) In each of the instant supply contracts, “A” is the Korea Asset Trust; “B” is the buyer; “B” is the Plaintiff respectively; “B” is the Plaintiff. Article 2 (B) (i) The loan related to the intermediate payment is within the scope of 40% of the total sales amount from the first intermediate payment after the conclusion of the contract with “B” to the extent of 40% of the total sales amount, but may be changed depending on the circumstances of the Plaintiff or the financial institution. (iii) The monthly interest repayment interest rate on behalf of the Plaintiff (joint and several surety by the soldier); and the entire repayment interest paid by the Plaintiff on behalf of the buyer shall be paid to the Plaintiff separately from the supply amount prescribed in Article 1.
The base date for the loan interest shall be the first date for the designation of occupancy designated by A, and the payment by A shall be made by the day immediately before the base date for the first designation of occupancy.