(영문) 서울행정법원 2018.11.22 2018구단11817
주거이전비 등 부지급 처분 취소
Text

1. The Defendant’s KRW 16,58,819 as well as 5% per annum from September 28, 2018 to October 31, 2018 to the Plaintiff.

Reasons

1. Facts of recognition;

(a) Outline of the improvement project - Business name: A project name: A project for the redevelopment and rearrangement of housing (hereinafter referred to as the “project in this case”) - Location and size: approximately 153,501 square meters in Seongbuk-gu Seoul Metropolitan Government C (hereinafter referred to as the “instant improvement zone”): A public announcement on the improvement plan - Defendant: A public announcement on the improvement plan: A public announcement on June 14, 2007, the Seongbuk-gu Seoul Metropolitan Government public announcement on the promotion plan for the renewal renewal acceleration of D E urban renewal acceleration district (draft): A public announcement on June 20, 2013

B. The Plaintiff’s residential situation - On March 2, 1989, the Plaintiff purchased the Seongbuk-gu Seoul Metropolitan Government Building 119 square meters (hereinafter “instant land”) and the above ground buildings (hereinafter “instant housing road name address is Seoul Seongbuk-gu L.”). On April 13, 1989, the Plaintiff continued to own the instant housing road name before being expropriated due to the instant project after completing the registration of ownership transfer on April 13, 1989.

- The plaintiff's domicile on the resident registration has changed as follows:

The date of the transfer of address 1 Seongbuk-gu Seoul Metropolitan Government G 1990 February 21, 1990, 1996 H apartment 106 Dong Dong-gun 505 March 19, 196, Seongbuk-gu Seoul Seongbuk-gu Seoul 20, 1996 December 3, 20, 1996, December 4, 2001, 196, 6. 3. 5, Seongbuk-gu, Seoul 201, 206. 14. 5, 206. 14. 5, 206. 3. 1, 205, Seongbuk-gu, Seoul, 201, 201, 3. 14. 5, 206. 8. 2, 201, 14. 14. 7. 2, 2008, 203

C. Adjudication on expropriation by the local Land Tribunal of Seoul Special Metropolitan City on August 25, 2017 - Land and buildings in this case owned by the Plaintiff - Land and buildings in this case - Compensation for losses: 33,200,000 won: 41,589,500 won and other obstacles: Acquisition of land, etc. for public works and acquisition of land, etc. for public works.