(영문) 서울중앙지방법원 2018.01.12 2017가합546885
구상금
Text

The Plaintiff

A. The Defendants are jointly and severally liable to compensate for KRW 132,932,70 and the Defendants from August 16, 2012 to November 13, 2017.

Reasons

Facts of recognition

A. The Plaintiff Co., Ltd. (hereinafter “Defendant Co., Ltd.”) entered into a limited trading agreement and joint and several sureties 1)

B) As indicated in the table below, a limit transaction agreement for guarantee and loan transactions (hereinafter collectively referred to as the “each limit transaction agreement of this case”) shall be deemed to be “each limit transaction agreement of this case” and a specific sequence transaction agreement shall be deemed to be “the O limit transaction agreement of this case”.

On December 28, 2010, the maximum amount of guarantee: 2,574,720,000 loans: the maximum amount of guarantee: 443,520,000 on December 28, 2010: 5,271,024,00 loans: 742,896,000 on December 28, 2010 to December 201, 2010: The maximum amount of guarantee: 5,271,024,00 loans: 742,896,000 on December 28, 2010 to December 27, 2013; and 3,03,003,000 loans: the maximum amount of guarantee under the B/3,000,000 loans: 443,520,000 on December 43, 200; and 3, 2017.

B. The Plaintiff issued a letter of guarantee under each of the instant Limit Transaction Agreements to the Defendant Company, and pursuant to the 1 Limit Transaction Agreements, the Defendant Company issued each of the guarantee certificates for construction works contracted by the Defendant Company from the secured creditors, as set out in No. 1 of the table below, and pursuant to the 2 and 3 Limit Transaction Agreements as set out in the table below, the Defendant Company issued each of the guarantee certificates for construction works contracted from the secured creditors.

The Defendant Company delivered the above guarantee documents to each secured creditor.

(1) The term “the instant guarantee” refers to the term “the instant guarantee” and the term “the instant guarantee” refers to the term “the instant guarantee”). On the date of issuance of a letter of guarantee for the type of guarantee for the name of guarantee for the guarantee creditor (the guarantee period), 1 Hyundai Construction (State), the guaranteed amount for the performance of the instant construction (State), 1.0,000,003 Hyundai Construction (State), from July 14 to December 31, 2011, 201, 306,873,016, 2.00,000,000 for the performance of the instant construction contract, from June 7, 2011 to June 30, 2012.

arrow