Text
1. The Defendant: (a) KRW 27,400,000 for the Plaintiff and KRW 6% per annum from August 1, 2014 to February 3, 2016; and (b) on the following day.
Reasons
1. Determination as to the cause of the instant claim: (a) around April 2014, the Plaintiff was awarded a subcontract from the Defendant for the completion cleaning of the completion cleaning among the Daejeon Seo-gu New Construction Works (Provided, That the payment deadline is the agreement to pay within 30 days from the date of receipt of the object); (b) the period from May 1, 2014 to May 30 of the same month; (c) the Plaintiff completed the completion cleaning but was paid only KRW 10 million from the Defendant on October 22, 2014; and (d) the Plaintiff was not paid KRW 27,40,000 from the Defendant on October 22, 2014; and (e) the purport of the entire pleadings is recognized comprehensively taking account of each of the statements in evidence Nos. 1, 2, and 3.
According to the above facts, the defendant is obligated to pay to the plaintiff the remaining service cost of KRW 27.4 million and the damages for delay calculated by the rate of 6% per annum under the Commercial Act from August 1, 2014 to February 3, 2016, and 15% per annum under the Act on Special Cases concerning the Promotion, etc. of Legal Proceedings from the next day to the date of full payment, as the plaintiff seeks.
2. citing the Plaintiff’s claim for conclusion