Text
1. Defendant B Co., Ltd.: (a) KRW 28,600,000 for the Plaintiff and the period from January 5, 2014 to September 30, 2015.
Reasons
1. Basic facts
A. On September 14, 2012, the Defendant Future Industry Development Co., Ltd. (hereinafter “Defendant Future Development”) entered into a contract with the Namyang Urban Corporation for the “C Creation Corporation” with the content of the contract amounting to KRW 122,760,00, total construction amounting to KRW 2,056,071,00, and the construction period from September 18, 2012 to December 18, 2012, with the content of the contract amounting to the extent of the amount calculated by deducting the primary contract amount from the total construction amount. Since the second contract entered into the contract after November 7, 2012, the contract was concluded by setting the contract amounting to KRW 1,93,311,00, total construction amounting to KRW 2,056,071,00, total construction perioding to KRW 2,000, and from November 7, 2012 to December 18, 2012 (hereinafter “instant”).
(hereinafter referred to as the “instant construction”) in total. B.
Since then, the Defendant’s future industrial development changed the contract amount from KRW 2,056,071,00 to KRW 2,053,942,00 on December 10, 2012 between the Namyang Urban Corporation and the Namyang Urban Corporation, and entered into a contract to change the construction period from September 18, 2012 to December 18, 2012 from September 18, 2012 to December 18, 2012.
C. On October 2012, Defendant future industrial development entered into a subcontract (hereinafter “instant subcontract”) with Defendant B Co., Ltd. (hereinafter “Defendant B”) by setting the total contract amount to KRW 1,018,417,400, and the construction period from October 18, 2012 to December 18, 2012, with respect to earth and sand works, water supply and drainage works, packing works, and metal hold works during the instant construction period.
Meanwhile, unlike the scope of construction stipulated in the instant subcontract, the Defendants agreed to collectively subcontract the instant construction work to Defendant B, and accordingly, the Defendant’s future industrial development agreed with Defendant B on November 201, 201 with respect to the entire construction of the instant construction work, at KRW 1,495,00,000, the agreed amount that Defendant’s future industrial development shall pay to Defendant B for the entire construction of the instant construction work.