Text
1. The Defendant’s disposition to suspend the participation of the Plaintiff on August 31, 2016 is revoked.
2. The costs of lawsuit shall be.
Reasons
1. Facts of recognition of the disposition, etc.;
A. On October 1, 2013, the Plaintiff: (a) received a contract from the Republic of Korea (B) for construction cost of KRW 168,481,200; (b) the date of commencement on October 7, 2013; and (c) the date of completion on December 20, 2013 (hereinafter “instant construction; and (d) received a contract for the “C Construction” (hereinafter “instant construction”); (c) October 25, 2013 (hereinafter “D”); and (d) completed the instant construction on December 18, 2013 (hereinafter “D”); (d) “rerefic concrete construction work” in the instant construction work; and (e) subcontracted the construction cost of KRW 19,602,00; and (e) completed the instant construction work on December 18, 2013.
B. The Ministry of National Defense conducted an audit of the instant facilities from March 9, 2015 to March 13, 2015, and notified the head of the Air Force Headquarters of the following audit results:
The design drawings of the instant construction are designed to be distributed at intervals of 200 meters, respectively, with the strength of ammunitions and sludges 21MPa, and the interior steel bars are designed at intervals of 200 meters x 200 meters and 150 meters x 150 meters.
D subcontracted a reinforced concrete construction among the instant construction works, was illegally carried out without using approximately 12 tons of the steel bars of 30 tons, a design quantity. As a result, it was confirmed that the inner steel bars of the wall and slobs respectively, average 260m x 305m x 266m x 300m m x 30m m.
(1) At the end of the standard for the name of the non-replacement of iron bars 1 and 240 m (m) and 305 m (310 m) and 40 m (260 m) and 300 m (200 m) and 310 m (310 m) and 310 m (310 m) and 310 m (260 m) and 260 m (310 m) and 310 m (30 m) and 240 m) and 310 m (300 m) and 240 m) and 305 m (310 m) of the 270 m (310 m) and 290 m) of the 3150 m (270 m) and 2810 m) of the 3010 m) structure design drawings at the same time.