(영문) 광주지방법원 2020.09.03 2018가단537833
공사대금
Text

The Plaintiff

A. Defendant B Co., Ltd.: 38,070,000 won and 22,770,000 won among them, from May 16, 2018 to 15.

Reasons

Judgment on the Grounds of Claim

A. Facts of recognition 1) The Plaintiff and Defendant B Co., Ltd. (hereinafter “Defendant B”).

() On April 19, 2018, the contract amount of KRW 75,900,00 for the contract amount, and the construction period from April 19, 2018 to May 15, 2018, Defendant B shall be the Plaintiff of Gwangju Northern-gu D ground buildings (hereinafter “instant buildings”).

(2) Around May 15, 2018, the Plaintiff entered into a contract with the Plaintiff to contract for the construction of the Rosterology. Around May 15, 2018, the Plaintiff completed the construction of the Rosterology, and was not paid KRW 22,770,00 among the construction cost. (2) In addition, the Defendant B contracted the Plaintiff with the construction of the 1st floor master crafts of the instant building on May 25, 2018, and the Plaintiff, around that time, performed electrical, lighting, equipment, and ducting construction.

Around June 18, 2018, the Plaintiff requested Defendant B to pay the down payment of the said construction work, but Defendant B did not pay the down payment to the Plaintiff, and the Plaintiff suspended the construction work of a master craftsperson around June 18, 2018 on the ground that the construction cost, such as Defendant B’s down payment, was not paid.

The construction cost for the portion executed by the Plaintiff until June 18, 2018 is KRW 15,300,000.

3) The Plaintiff and Defendant C Co., Ltd. (hereinafter “Defendant C”).

(2) On February 23, 2018, the contract amount is KRW 258,500,000 for the contract amount and the construction period is from February 23, 2018 to March 31, 2018, and Defendant C is the Plaintiff’s underground floor, the second, and the third floor repair work of the instant building (hereinafter “building 1 repair work”).

A) A contract was concluded with the Plaintiff to conclude a contract. Around March 31, 2018, the Plaintiff completed the said construction, and the Plaintiff was not paid KRW 77,500,000 out of the construction cost. (4) Defendant C concluded a contract for the repair of the first floor among the instant buildings by setting the contract amount of KRW 139,70,000 and the construction period of KRW 139,70,000 on April 19, 2018 from April 19, 2018 to May 15, 2018.

The Plaintiff completed the above construction work on May 15, 2018, but was not paid KRW 41,910,000 out of the construction cost.

[Reasons for Recognition]