(영문) 광주지방법원 2014.05.15 2013가합53047
손해배상(기)
Text

1. The defendant Cheongju Construction Co., Ltd. is 100,096,00 won for the plaintiff A, 75,307,000 won for the plaintiff B, and 33.

Reasons

1. Basic facts

A. The status of the parties (1) Plaintiff A solely owns 39,964m2 (hereinafter “F salt farm”) in Yong-gun, Young-gun, Jeonnam-gun, and owned 2/21m2 of the 38,261m2 of the 2/21m2 of the 38,261m2.

On the other hand, Plaintiff A entered into a contract for salt production in H and F salt farms, and H transferred all the claims for damages arising from flood accidents in the above salt farms to Plaintiff A, and on December 12, 2013, Plaintiff A sent the notice of transfer of rights to the said transfer to the Defendants by content-certified mail.

(2) The Plaintiff B and C share 40,000 square meters per 1/2 shares in the 1/2 shares in the previous Yong-gun, Young-gun, Jeonnam-gun, and the Plaintiff C shares 2/21 square meters in the 38,261 square meters of the 2/21 square meters of the 38,000 square meters of the 201 square meters of the 3

On the other hand, K, which produced salt at the J salt farm, transferred all claims for compensation for damage caused by flooding in the above salt farm to Plaintiff B, and on January 15, 2013, K sent the notice of transfer of rights to the Defendants by content-certified mail.

(3) The Plaintiff B and D share 40,000 square meters (hereinafter “M salt farm”) in 1/2 shares, respectively, in the area of 40,000 square meters (hereinafter “M salt farm”). Plaintiff D shares 2/21 square meters in the area of 38,261 square meters in the area of 2/21 square meters in the area of Jeonnam-gun, Jeonnam-gun.

On the other hand, the N, which produced salt in M salt farms, transferred all of the claims for compensation for damage caused by flood accidents in the above salt farms to Plaintiff B, and on January 15, 2013, the notice of transfer of rights, the contents of which are the above transfer, was sent to the Defendants by content-certified mail.

(4) On December 28, 2011, Defendant Young-gun (hereinafter “instant tide embankment”) managed a P region from January 3, 201 to December 17, 2012, 201, with regard to the construction of the Cheongnam-gun’s Oscopic bank (hereinafter “Defendant Cheongju-gun Construction”), the total construction period of the construction period, the total construction period of which is KRW 1,012,574,890, and the total construction period.