(영문) 서울중앙지방법원 2018.03.08 2017가단5086077
용역비
Text

1. The Defendant’s KRW 23,826,00 for the Plaintiff and 6% per annum from October 1, 2015 to March 8, 2018.

Reasons

1. Basic facts

A. The Plaintiff is a private entrepreneur who operates a business support service business, etc. with the trade name of Seongbuk-gu Seoul Metropolitan Government, and the Defendant is a housing redevelopment project partnership established for the B housing redevelopment project with the size of 104,979.30 square meters in Seongbuk-gu Seoul Metropolitan Government as a project implementation district (hereinafter “instant project implementation district,” and “the project implementation district of this case”).

B. On January 5, 2015, the Plaintiff and the Defendant concluded a emigration promotion service contract (hereinafter “instant service contract”) and the part related to the instant case is as follows:

(hereinafter referred to as "A" and "B" refer to "the defendant" and "the plaintiff"). For a housing redevelopment improvement project (hereinafter referred to as "party project") B in the contract for relocation promotion service B, the head of the B Housing Redevelopment and Improvement Project Association E (hereinafter referred to as "A") and the representative of C representative Director who is the beneficiary.

A (hereinafter referred to as “B”) shall prepare two copies of this Agreement for the purpose of proving that the terms and conditions of the Agreement are agreed as follows and annexed, and shall keep one copy after signing and sealing A and B, respectively.

- - Future -

1. Contract name: Emigration services;

4. Service period: From the date of conclusion of the contract to the date of completion of the relocation period.

5. Contract amount: The value of supply in the lump sum of KRW 550,000,000 (Won 550,000,000): The value of supply in the lump sum of KRW 50 million (Won 500,000,000): the value of KRW 50,000 (Won 50,000,

6. Method of payment of the price: From 30 days to 30 days after commencement of the service of non-high-end down payment, 70% per month based on the resettlement rate of the households subject to progress payment of the additional 70% per month, 350,000,000 additional 10% per month.

7. Incentives and service costs: To be paid in full when 95 percent relocation is completed by the end of April 2015.

(343 households of the current household of the unpaid household)

8. Incentives: Addition of daily gold of 50 million won (Won 50,000,000):

1.The terms and conditions of a service contract, Article 3 (Period of Work) of the Terms and Conditions of the service contract, shall be from the date of conclusion of the contract.