(영문) 대구지방법원김천지원 2016.11.24 2016가단32786
손해배상금등 청구의 소
Text

1. The Defendant: (a) KRW 107,905,336 to the Plaintiff and KRW 5% per annum from September 2, 2016 to November 24, 2016; and (b) from the following day.

Reasons

1. On April 20, 2016, the Plaintiff (seller A) entered into a sales contract with the Defendant (Buyer B) on the entire part of the non-performance of steel, scrap iron, and oil (hereinafter “instant sales contract”) with the following content as to the total amount of 1,700 tons of Samsung Group A (B, 2 workplace) in Ulsan-gun Group A (B, 2 workplace).

(1) The sale and purchase price of Article 2. 1. 1. 2. The sale and purchase price of the subject matter: 600 won per kilogram 1. 2. The subject matter of the sale and purchase: the subject matter of the sale and purchase price of the subject matter of the sale and purchase (including value added tax) shall not guarantee the weight of the subject matter of the sale and purchase because the subject matter of the sale and purchase of the subject matter of the sale and purchase price of the subject matter of the sale and the subject matter of the sale and purchase price of the subject matter of the contract (excluding stones) is purchased at the unit price per kg. The subject matter of the sale and purchase price of the subject matter of the sale and the subject matter of the sale and purchase price of the subject matter of the vehicle of the vehicle of the vehicle of the vehicle of the Party of the Party of the sale and the subject matter of the sale may be shipped after full payment of the purchase and sale price of the vehicle of the Party of the purchase and sale, and the vehicle of Party B shall be added by the weight and the unit price of the vehicle of the shipment (600 won).

B Within April 21, 2016, the entire quantity of the subject matter of sale loaded inside the workplace of “A” must be taken out from the workplace of “A” and the burden of all legal and economic expenses incurred due to the failure to complete shipment within April 21, 2016.

2) The order of taking out the subject matter to be sold shall be taken out in the order designated by A, and if the order of taking out is not complied with or is not faithfully carried out, A may immediately destroy the contract. 1) B must take out all the subject matter of sale, excluding stones, until April 21, 2016, the final date of taking out the subject matter of the contract.

However, even though Eul has performed its best shipping operations, it was not completed until April 21, 2016.