(영문) 울산지방법원 2018.04.24 2017가단52964
양수금
Text

1. The Defendant’s KRW 61,181,373 as well as the Plaintiff’s KRW 5% per annum from March 21, 2017 to April 24, 2018.

Reasons

1. Basic facts

A. The Plaintiff is a company with the purpose of metal sales and metal processing and production, special lecture export and import business, etc.

B. The Plaintiff has traded metal processing with C Co., Ltd. (hereinafter “Nonindicted Company”). The Plaintiff’s credit payment obligation against the Plaintiff of Nonparty Company is KRW 170 million as of July 7, 2016.

C. On October 2, 2014, the Defendant entered into a gold supply contract with the Plaintiff as the manufacturer of the U.S. automobile parts, setting the total contract amount at USD 862,341 with the Nonparty Company as US dollars 862,341 (hereinafter “instant supply contract”), and the specific details are as follows.

Article 1. Contract Project Name: The number of items subject to J: 2 (HEADER INN LH/RH 101 products and products of SUPPPPPO ME ME MH/RH 107) 10 sets manufacturing scope: from 3D designs to the completion of improvement works when H/L/T/O/O problems occur.

Provided, however, after the domestic B/OF approval, costs of local improvement costs are to be borne after determination as to whether they were responsible: Maximum inspection approval and H/L/O problems: - Total production and packing, arrival [air code] - 300 production to be linked at the time of approval of B/OF approval. The defendant shall pay to the non-party company 15 per cent (129,351.15 US dollars) first 20% (172,468.2 US dollars): 3rd 15 per cent (129,351.15 US$) after the end of 25th 15th 15th 15th 15th 15th 15th 15th 15th 15th 15th 15th 15th 15th 26th 15th 15th 4th 15th 6th 15th 204th 15th 204th 15th 4th 15th 6th 4th 15th 4th 6th 6th 4th 4th 4).4.

D. On March 27, 2015, the Defendant also agreed to the non-party company at USD 58,86.15 on the design modification service for the product No. 107 under the instant contract (amended due to business fluctuations).