logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 인천지방법원 2015.11.11 2015가단223403
공사대금
Text

1. As to the Plaintiff KRW 20,500,000 and the above money, the Defendant shall pay to the Plaintiff KRW 131,40,000,00 from March 1, 2014, and KRW 110,00.

Reasons

1. Determination as to the cause of the Plaintiff’s claim

A. (1) On March 2013, 2013, the Plaintiff was awarded a subcontract for the construction period of B neighborhood living facilities from March 20, 2013 to February 28, 2014 and completed the said construction work, and was not paid KRW 20,50,000 out of the said construction cost, and (2) around April 2014, 2014, the Cfactory New Construction Work period was from April 1, 2014 to April 1, 2014.

9. Until August 31, 201, the contract amount of KRW 407,00,000 has been subcontracted and completed, and the above construction has not been paid KRW 110,00,000 among the above construction costs, and (3) around August 1, 2014, the D construction has been subcontracted and completed the construction period of KRW 9,90,000, and the above construction has not been paid KRW 900,000 among the above construction costs has not been disputed between the parties, or there is no dispute between the parties, or there is no receipt of KRW 1-3,00,00,00 among the above construction costs, by comprehensively taking into account the overall purport of oral arguments as to the items in subparagraphs 1-1 through 9, 2-1 through 7, 3-1, 2-3, 3-1, 2, and 3.

B. According to the above facts, the Defendant is obligated to pay the Plaintiff the total amount of KRW 131,40,000 for the accrued construction cost of KRW 110,50,000 (2) unpaid construction cost of KRW 110,500,000 (3) unpaid construction cost of KRW 110,500,000) and the above amount of KRW 20,500,000, which is after the completion date of each construction work, from March 1, 2014 to October 1, 2014; KRW 90,000,000 from May 1, 2015 to June 30, 2015; and to pay damages for delay at the annual rate of KRW 5,500 prescribed by the Civil Act from the following day to the date of service of a copy of the complaint of this case until June 30, 2015; and to pay damages for delay of 10,500,000 per annum.

2. Determination on the Defendant’s assertion

A. As to this, the defendant's employees are the defendant's representative director's funds in the process of concluding a subcontract with the subcontractor including the plaintiff.

arrow