Text
1. As to the Plaintiff KRW 60,000,000 and its KRW 20,000 among them, the Defendant shall pay to the Plaintiff KRW 10,000,000 from December 31, 2008.
Reasons
1. The Defendant with the indication of the claim borrowed KRW 10 million from the Plaintiff on April 16, 2008, and KRW 10,000 on May 9, 2008 as the repayment date on December 30, 208, and borrowed KRW 10,000 on May 26, 2009 as the repayment date on October 25, 2009. On September 30, 2009, the payment date was set as KRW 30,000 on September 30, 2010, but without returning the above principal and interest on the loan. Thus, the Defendant is demanding payment of the principal and interest on each of the above loans and damages for delay from the day following the repayment date to the day of full payment.
2. Article 208 (3) 3 of the Civil Procedure Act applicable provisions of Acts.