(영문) 서울고등법원 2017.08.22 2017나2000832
보증채무금
Text

1. Of the judgment of the court of first instance, to Defendant Specialized Construction Mutual Aid Association that is equivalent to the following payments:

Reasons

1. Basic facts

A. The Plaintiff’s status as the Korea Land and Housing Corporation (the Korea Land and Housing Corporation became the Korea Land and Housing Corporation in consequence of a merger with the Korea Land and Housing Corporation on October 1, 2009; hereinafter “Korea Land and Housing Corporation”) is a project proprietor who constructed and sold the 13-dong 990 households of the Seosan-dong, Seosan-dong 295, Seosan-dong, Seosan-gu, Daejeon (hereinafter “the apartment of this case”), and the Plaintiff is the contractor of the instant apartment of this case.

B. The Plaintiff entered into a subcontract, among the apartment construction of this case, subcontracted the construction work of this case, the construction work of 1 section 1 section 1 section 1 section 1 section 1 section 1 section 2 to the Namdo Co., Ltd. (hereinafter “Namdo”), the construction work of 1 section 1 section 2 section 1 section 1 section 2 structural structural structural structural structural structural structural structural structural structural structural structural structural structural structural structural structural structural structural structural structural structural structural structural structural structural structural structural structural structural structural structural structural structural structural structural structural structural structural structural structural structural structural structural structural structural structural structural structural structural structural structural structural structural structural structural structural structural structural structural structural structural structural structural structural structural structural structural structural structural structural structural structural structural structural structural structural structural structural structural structural structural structural structural structural structural structural structural structural plant

C. On June 26, 2009, from July 1, 2009 to June 30, 2019, 229,936,920, Namnam Construction, June 26, 2009, 162,596,910 South C&D A, from July 1, 2009 to June 30, 201, entered the warranty contract in violation of the warranty warranty agreement as follows: (a) from July 1, 2009 to June 30, 2009, 162,596,910 South C&D A, from July 30, 2019 to June 30, 209; and (b) from November 27, 2009 to November 21, 2009 to June 8, 204, 205; and (c) from the respective warranty warranty agreement, the warranty agreement was entered in the respective warranty warranty agreement as the warranty agreement.