(영문) 광주지방법원 2015.06.18 2014가합4691
양수금
Text

1. The plaintiff's claim is dismissed.

2. The costs of lawsuit shall be borne by the Plaintiff.

Reasons

1. Basic facts

A. 1) Co., Ltd. (hereinafter “C”) (hereinafter “C”).

On February 6, 2007, the service contract (hereinafter “instant service contract”) with the content as follows as the establishment promotion committee of B apartment reconstruction and improvement project cooperatives (hereinafter “instant service contract”).

AB concluded the agreement.

1. Project name: A housing reconstruction project for B apartment houses;

2. Details of the contract: Specialized management services for the implementation of the rearrangement project for B apartment reconstruction.

3. Location: Seo-gu, Gwangju, and six parcels.

4. Total contract amount: 2.1% (excluding value-added tax) of the total project cost (including expenses for survey, design, service cost, designation of a rearrangement zone, service cost for environmental impact assessment, traffic impact assessment service cost, traffic impact assessment service cost, etc., and service cost for the implementation of all affairs

5. Term of a contract: The scope of services to be performed by Article 3 (Scope of Services) C from the contract to the settlement of a project shall include basic services under the contents of a contract, additional services or special services as determined by a consultation between the defendant and C, and all kinds of services performed after the selection of construction works after the completion of a contract including construction and land use plan expenses (including construction and land use planning expenses, project analysis expenses), interest-free loans, and service expenses included in the service expenses referred to in Article 4 (including construction and land use planning expenses, project analysis expenses), and design services expenses (including construction and land use plan expenses, project analysis expenses), geological survey expenses, current status and boundary survey expenses, maintenance zone designation expenses, environmental impact assessment expenses, traffic impact assessment expenses, traffic impact assessment service expenses, cultural heritage table survey expenses, cooperative members' rights analysis service expenses, project implementation approval expenses, etc.;

Article 4 (Calculation of Service Costs and Payment Method) The Service Costs shall be 2.1% of the total project costs, and the value-added tax shall be separate, and the Service Costs shall be paid in installments after the selection of the Project:

After selecting 60% of the total contract amount of the first installment due to the payment period of the Gu, the third installment after the plan for management and disposal of 20% of the total contract amount of the second installment after the selection of the construction project.