Text
Defendant shall be punished by imprisonment for a term of one year and six months.
300,000,000 won shall be additionally collected from the defendant.
Reasons
Punishment of the crime
On March 1, 1998, the Defendant entered the Jongno-gu Seoul Metropolitan Government E (State) Construction. From July 1, 2012 to July 10, 2013, the head of the Ministry of Foreign Affairs is working as the head of the Foreign Affairs Purchase Division, and was in charge of the overall affairs of the contract, such as the selection of contracting companies related to construction ordered by F, the adjustment of construction amount, etc.
On October 2012, the Defendant: (a) bid to the pipeline construction of a fertilizer plant that is scheduled to be established in G area that was ordered to be built in G area (ju), and (b) bid to the representative director of H (ju) H selected as a minimum bidder; and (c) bid price is changed to KRW 300,000,000 in return for bid price.
On October 31, 2012, the Defendant received 100,000,000 won in cash from K, which is a middle restaurant in Jongno-gu Seoul Jongno-gu, Seoul, for the consideration of raising the contract amount from I, and 100,000,000 won in cash under the same name as I, from the G, from the main point of a string where the trade name in Jongno-gu Seoul, is unknown around November 29, 2012, from the main point of a string where it is impossible to know around December 14, 2012, the Defendant received from I the 10,000,000 won in cash under the same name as I, respectively.
As a result, the Defendant received a total of KRW 300,000,000 in response to the illegal solicitation related to the pipeline construction of a fertilizer plant that was ordered to construct (ju) F.
Summary of Evidence
1. Statement by the defendant in court;
1. A protocol concerning the interrogation of the accused by the prosecution;
1. Each prosecutor's statement concerning I, L, M, or N;
1. Investigation report (to be accompanied by a statement submitted), investigation report (the organization of the head office of F Construction), investigation report (the confirmation of the current working department of a suspect A), investigation report (the results of investigation of funds sources granted to a suspect A), investigation report (the results of investigation of funds sources granted to a suspect A), and investigation report (the analysis of data related to bidding of F F F Construction Order pipeline construction works);
1. Application of the summary of the pipeline construction of G fertilizer factory in the second half of the year of 2012, the G fertilizer pipeline construction contract in the second half of the year of 2012, and the estimated submission of H;
1. Relevant Articles of the Act and punishment concerning the facts constituting the crime;