(영문) 서울서부지방법원 2017.02.09 2015가합36273
지연보상금청구 등의 소
Text

1. The Defendant’s KRW 193,892,00 for the Plaintiff and KRW 5% per annum from October 1, 2015 to February 9, 2017.

Reasons

1. Facts under the basis of facts may be found either in dispute between the parties or in Gap evidence 1 to 15 (including branch numbers if there are branch numbers; hereinafter the same shall apply) and Eul evidence 1, together with the whole purport of the pleadings. A.

1) On July 28, 2010, the Plaintiff received a contract from the Defendant for the construction period of construction of the construction of the Yeongdeungpo Nuclear Headquarters substitution Site on the land outside of 1373-1, Hongnam-gun, Hongnam-gun, Hongnam-gun, with the construction period of construction from August 2, 2010 to November 13, 2013 (including value-added tax). The Plaintiff completed the construction (hereinafter referred to as the “instant construction work”), and the Plaintiff completed the construction (hereinafter referred to as the “instant construction work”), and the said construction contract is referred to as the “instant construction contract.”

2) Since then, the Plaintiff agreed to modify the content of the instant construction contract on 11 occasions with the Defendant.

(3) The construction work completion date of the construction contract shall be extended on May 18, 201 to 35,41,41,061, and the construction work completion date of the construction contract shall be extended to 36,61,64,00 won on September 25, 201; and the construction work completion date of the construction contract shall be extended to 36,64,00 won on April 30, 201 to 39,000 won; the construction work completion date of the construction contract shall be extended to 39,023,06,557 won on April 30, 201; and the construction work completion of the construction contract shall be extended to 41,00,000 won on May 18, 2013 to 30, 2015; and the construction work completion of the construction contract shall be extended to 36,50,000 won on April 19, 2013;

The terms used in this case are defined as follows:

5. The term “design” means: