logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 의정부지방법원 2016.06.29 2015가합4372
인센티브지급청구
Text

1. The plaintiff's claim is dismissed.

2. The costs of lawsuit shall be borne by the Plaintiff.

Reasons

1. Basic facts

A. On October 4, 2013, the Defendant obtained a construction permit for the new construction of a golf course on the 8 parcels outside Macheon-si, B, and commenced construction work from Ma (after that, the name was changed to D).

On October 5, 2013, the Defendant ordered the Plaintiff to build a club club (hereinafter “instant club”) and a military unit among the instant golf club (hereinafter “instant club”), and agreed to include the following:

(hereinafter “the instant construction contract”). The construction site: The construction completion date of the construction period of YY B (DD site): The date the Defendant secured working conditions: The completion date: April 30, 2014; - The completion of the construction of the structural and external windows up to the second floor of the ground until December 15, 2013 (the environment in which the interior of the first floor and the first floor is possible) - the management warehouse up to the second floor of the ground until December 15, 2013: the completion date of construction by December 15, 2013 - the construction completion permission by April 30, 2013: The construction completion permission by April 30, 2013 - the construction completion permission is extended to the extent that it is impossible for the construction work to be heated and heated due to delay or depression due to reasons attributable to the Defendant on May 30, 2014.

(The contract amount shall be applied as of October 1, 2013, which is the first starting date. The contract amount: 4.766 billion won: the scope of the contract 1) the club and the unit operation (the management Dong, the guard room, the two unit, and the structure of the sewage treatment plant) all the construction works within the construction period under Article 3 of the terms of the contract. When the construction is completed within the construction period under the terms of the contract, the defendant shall pay 15% of the contract amount to the plaintiff as incentives.

However, all construction works such as civil engineering and construction are conditions under which the plaintiff is appointed as field agent and quality manager and the plaintiff is responsible and managed at the time of registration of sports facilities.

On May 16, 2014, the Plaintiff and the Defendant agreed to extend the completion date of the instant construction contract to June 20, 2014, and again, the completion date on October 16, 2014 is October 21, 2014.

arrow