(영문) 춘천지방법원 2013.09.04 2013가합140
토지인도
Text

1. The principal suit against the Defendant (Counterclaim Plaintiff) B and the Defendant (Counterclaim Plaintiff) C shall be dismissed, respectively.

2...

Reasons

A principal lawsuit and counterclaim shall also be deemed a principal lawsuit and counterclaim.

1. Basic facts

A. (1) The Gangwon-do Governor of Gangwon-do shall undertake the project implementation process on May 20, 2010 (amended by Act No. 9861, Dec. 29, 2009; hereinafter “National Land Planning Act”).

) Pursuant to Article 30, Hongcheon-gun G G (hereinafter “instant project implementation district”).

3) The Hongcheon Management Plan Decision for the Creation of the Hongcheon Golf Co., Ltd. (hereinafter referred to as the “Determination of the Hongcheon Management Plan”).

(2) On September 7, 2010, the head of Hongcheon-gun announced that the Plaintiff Company was designated as the implementer of the Redcheon-gun Urban Planning Facility (sports facilities: golf courses, riding courses) project, and publicly notified as the M&D on July 22, 2010 pursuant to Article 32 of the National Land Planning and Utilization Act (amended by Act No. 10599, Apr. 14, 201). The head of Hongcheon-gun, who was delegated with authority by the Governor of Gangwon-do, designated the Plaintiff Company as the implementer of the Redcheon-gun Urban Planning Facility (sports facilities; riding courses); and publicly notified as the M&D notification of Hongcheon-gun.

3) Pursuant to Articles 88 and 91 of the National Land Planning and Utilization Act (amended by Act No. 10599, Apr. 14, 2011), the head of Hongcheon Gun may operate a golf course business with respect to the instant project site, which is a sports facility with respect to the instant project site as follows (hereinafter “instant project”).

2) Authorization of the implementation plan (hereinafter “authorization of the implementation plan of this case”)

The results are as follows: ① the location of the project site - the golf course: G Day in Chuncheon City - the type and name of the business - The type of red-dried Gun planning facility (sports facility: golf course, riding club business): the name of the golf course: the size of the facility for the creation of the H golf set, 1,316,210 public golf course, 18 persons and clubs, 3,000,000,000.