Text
1. The Defendant’s KRW 355,724,930, and the Plaintiff’s annual rate from May 8, 2013 to December 31, 2014.
Reasons
1. Basic facts
A. The Defendant entered into a contract for construction works between the Defendant and A Co., Ltd. on March 13, 2012 (hereinafter referred to as “A”) with the Seosan-si Co., Ltd. (hereinafter referred to as “A”). The construction of a multi-family house for one complex on the ground (the instant land was divided into 697 square meters from the foregoing land on August 3, 2012) (the total floor area of the instant house was 1st, 4st, and 969.5 square meters on the ground, including the total floor area, 9.5 square meters on the register of the register, 9.5 square meters (the 1st, 259.6 square meters, 1st, 58.07 square meters on the 1st, 21.61 square meters on the 2nd, 210.07 square meters on the 3rd, 210.07 square meters on the 3rd, 2107 square meters on the 1st, etc.).
At the time, the contract conclusion was conducted between the defendant and the Eul's representative.
B. A around May 2012, a contract for construction works between the Defendant and E was concluded between the Defendant and the E Company, and the construction was suspended upon completion of the underground floor, the ground floor and the 1st floor of the instant housing, and the ceiling construction. The Defendant is the E Company on July 25, 2012 (hereinafter “E”).
B) In conclusion, the instant construction contract was concluded between the Defendant and the construction cost of KRW 850,00,000 (excluding value-added tax) and the construction period from August 1, 2012 to October 31, 2012, and agreed that “E succeeds to the construction contract between A and the Defendant” as a special agreement (hereinafter “instant contract”).
(2) Meanwhile, on November 14, 2012, the Defendant drafted a written agreement between F and F acting on behalf of E as follows.
Written Consultation
1. As to the documents required to be attached to the conclusion of the contract document prepared by the defendant and E.