1. The defendant shall pay 80,000,000 won to the plaintiff and 15% per annum from February 8, 2019 to the day of complete payment.
Reasons
From June 2, 2016 to November 9, 2018, the Plaintiff supplied the Defendant with goods, such as tegrative rhesion material, to the Defendant. The fact that the Defendant’s price for the goods unpaid is no dispute between the parties, or that the Defendant’s price for the goods is 80 million won, can be acknowledged by considering the overall purport of the pleadings as a whole in the statement in subparagraphs 1 through 4.
According to the above facts, the defendant is obligated to pay to the plaintiff damages for delay calculated at the rate of 15% per annum from February 8, 2019 to the day of full payment, which is the day following the delivery of a copy of the complaint of this case claimed by the plaintiff.
The plaintiff's claim is accepted.