Text
The plaintiff's claim against the defendants is dismissed in entirety.
Litigation costs shall be borne by the plaintiff.
Reasons
1. Basic facts
A. The Plaintiff is a company engaged in civil engineering, construction work, industrial equipment construction work, etc.
B. On May 2014, the Plaintiff was awarded a contract with the Korea Development Corporation for D Business Uniforms and Maritime Plants Facilities (hereinafter “instant construction”).
The instant construction consists of the construction of a fish farm in the sea area of Jindo-do, Jindo-do, Jindo-do, the installation of a fish farm, the United States, the width of 100 meters x the construction of a fish farm in the size of 100 meters in length (hereinafter referred to as “the construction of a fish farm in this case”).
The main contents of the Project include the Plaintiff’s anchoring of concrete materials on the ground, setting anchors to the sea to fix the sea bed and then completing one set of facilities by linking the body with the father on the ground surface and the father by linking it to the part on the surface of the sea.
(c)
During the construction of the instant case, the Plaintiff, while carrying out the construction of the instant construction, has caused the phenomenon of “rodings connected to anchors” to be tangled with each other, and during the dispute between the Plaintiff and Jeonnam-do about the responsibility, the Plaintiff was taking temporary suspension measures against the instant seaweeds breeding project around December 2, 2016.
Accordingly, on March 2018, the Plaintiff filed an application with the F agency for arbitration against Jeonnam-do, and the F agency rendered an arbitration ruling to the effect that the Plaintiff will perform additional construction to resolve the phenomenon of the laf and that subsequent construction costs will be borne by the Plaintiff and Jeonnam-do divided into 1:1.
After the ruling of the court, Jeonnam-do rendered the Plaintiff a temporary suspension of the business of this case, and notified the Plaintiff of the cancellation and resumption of construction of the business of this case on April 2018.
(d)
On April 2018, the Plaintiff puts anchors into G around G with a diving line either sweaked or cut, during the course of the construction of the seaweeds of this case (hereinafter “the Plaintiff”) and connects G with G 89 boats (hereinafter “the Plaintiff”).