logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 청주지방법원 2013.09.26 2012가단19765
임대료 등 청구의 소
Text

1. The plaintiff's claims against the defendants are all dismissed.

2. The costs of lawsuit shall be borne by the Plaintiff.

Reasons

1. Basic facts

A. On August 1, 2011, Defendant Call Lbnb Co., Ltd (formerly, Co., Ltd., Ltd.; hereinafter “colbnb”) entered into a contract for the construction of the instant construction work to Nuri Construction Co., Ltd. (hereinafter “Nuri Construction”) located in the 2 general industrial complex 11st block, Chungcheongnam-gun, Chungcheongnam-gun, and entered into a contract for the instant construction work to Nuri Construction Co., Ltd. (hereinafter “Nuri Construction”). The Nuri Construction subcontracted the instant construction work to Nuri Construction Co., Ltd. (hereinafter “New Construction”).

B. On August 11, 2011, the Plaintiff entered into a temporary re-lease agreement with the New Co., Ltd., and the Nuriby Construction jointly and severally guaranteed the obligation under the said lease agreement to the Plaintiff of the New Co., Ltd., and the Plaintiff leased the temporary materials at the instant construction site, and New Co., Ltd. established the said temporary materials at the instant construction site and performed the construction work.

C. On December 12, 201, when the instant construction was in progress, there was a default on the Social Construction, and at that time, New Heavy Construction was completed at the construction site of this case. Accordingly, the instant construction was suspended.

Since then, on March 2, 2012, Defendant Qannb contracted the remaining construction during the instant construction to the Peace Construction Co., Ltd. (hereinafter “P peace Construction”), and Defendant Peace Construction resumed the construction from around that time to June 13, 2012.

E. Meanwhile, Defendant Peace Construction: (a) drafted a written subcontract between the Plaintiff and the construction cost of KRW 11,880,00 on March 5, 2012; (b) the construction period from March 5, 2012 to March 31, 2012; (c) the construction cost of KRW 882,695 on March 15, 201; (d) the construction period from March 15, 2012 to June 15, 2012; and (e) concluded a lease agreement on the remaining temporary facilities by preparing each written subcontract agreement between the Plaintiff and the construction period of KRW 712,910 on March 15, 201 and March 15, 2012 to June 15, 2012; and (e) subsequently, paid the amount equivalent to the said payment to the Plaintiff.

F. The plaintiff.

arrow