(영문) 전주지방법원 2015.10.22 2015고단954
사기
Text

Defendant

A Imprisonment with prison labor for one year, for eight months, and for six months, for each of the defendants C.

except that this judgment.

Reasons

Criminal facts

[criminal power] On December 16, 2014, Defendant A was sentenced to 6 months of imprisonment with prison labor and 2 years of probation for fraud, etc. at the Jeonju District Court on December 16, 201, and the above judgment became final and conclusive on the 24th of the same month, Defendant B was sentenced to 1 year of imprisonment with prison labor and 2 years of suspended execution for fraud, etc. in the Jeonju District Court’s branch branch on December 16, 2014. The above judgment was

【Criminal Facts】

1. From the beginning of April 2014, the Defendants: (a) concluded a lease contract with Defendant B using 30,000 square meters of G 30,000 square meters of G from H to May 2, 2016 in the name of “F of the limited liability company”; (b) instead, the Defendants were able to collect marina sand from the said land by receiving money from the victim I as if they were able to collect marina sand immediately after obtaining permission, even though they did not obtain permission for collecting marina sand from the said land.

피고인들은 2014. 4. 16.경 정읍시 J에 있는 피고인 B의 집에서, 피고인 A은 피해자에게 ‘이미 정읍시로부터 위 임야에서 마사토를 채취할 수 있는 허가를 받아놨고, 마사토의 양이 40만㎥ 루베 정도이며, 1㎥당 4,000만 원만 받아도 16억 원을 받을 수 있고, 사업 경비로 5억 원을 제한다고 하더라도 순수익이 10억 원은 되며, 허가를 받기 위해 이미 약 4억5,000만 원 정도를 들였는데, 8,000만 원만 투자하면 지분 25%를 주겠다’는 취지로 거짓말하였다.

In addition, Defendant B displayed documents related to the permission, such as an application for permission for development activities, a business plan, a real estate lease agreement, and a written consent of residents, which he/she had owned by the victim, and Defendant C also took equipment in line with the horses of Defendant A and B.

However, the fact was that it was impossible to collect marina sand in the above forest because it was not permitted to collect marina sand from the Si of Jung-Eup.

arrow