logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 의정부지방법원 2021.01.29 2019가합51871
청구이의
Text

1. The Defendant’s payment order for the contract deposit case against the Plaintiff at the Jung-gu District Court, 2015 next 214.

Reasons

1. Basic facts

A. C Co., Ltd. (hereinafter “C”) obtained a building permit (hereinafter “instant building permit”) on June 19, 1993 to build religious facilities (water sources) on the land of Dongbcheon-si, Dongbcheon-si, E, and F, and commenced a new construction work under a contract to G, but the construction was suspended until the end of 194 while the construction was completed.

2) On October 16, 1995, D transferred the building permit to C, and decided to construct the building to be newly built in two Dongs, and obtained the building permit (hereinafter “instant building permit”) with the content that the size of the land was changed from E, E, F, H, F, I, J to a religious facility (a water source) into two units, such as the 4th floor on the ground where the size was newly constructed, the 4th floor on the ground, the 4th floor on the ground, the 1st floor on the ground, the 1st floor on the ground, and the 1st unit on the ground (K), and the 1st unit on the ground (L) on the ground.

3) C succeeded to the contract entered into between D and G, and currently is the former representative director of the Defendant and the former representative director of M&A and N&A at the time.

O has contracted L Newly constructed construction work.

4) Although the construction has been resumed, by the end of May 1998, G filed a lawsuit seeking payment of the construction cost against C as 2987, for lack of the payment of the construction cost, for the reason that G did not receive the construction cost, and the said court rendered a favorable judgment in favor of G to the effect that C would pay KRW 80 million and delayed damages to G, and the said judgment became final and conclusive on June 11, 1999, on June 11, 1999.

6) G is limited to KRW 300 million on April 7, 1999, and KRW 350 million on February 1, 2001, from P (the name before the Plaintiff’s representative director’s opening of Q, hereinafter “P”).

arrow