Text
1. The Defendant shall pay to the Plaintiff KRW 50,00,000 and the interest rate of KRW 15% per annum from April 26, 2016 to the day of complete payment.
Reasons
1. The Plaintiff: (a) borrowed KRW 10 million in cash from the Credit Guarantee Foundation on March 30, 201 to the Defendant; (b) borrowed KRW 495,00 from the New Savings Bank on November 14, 201 to transfer KRW 3 million from the Defendant’s corporate bank account; (c) borrowed KRW 7 million from the HK Savings Bank on October 7, 201 to the Defendant’s corporate bank account; and (d) transferred KRW 14 million from the BSF Capital on March 8, 201 to the Defendant’s corporate bank account; and (e) transferred the loan from the Defendant’s corporate bank account on March 28, 201 to the Defendant’s corporate bank account; and (e) transferred the loan from KRW 14 million to the Defendant’s corporate bank account on March 2, 2011 to the Defendant’s overall account by borrowing KRW 10 million from Hyundai Savings Bank on March 2, 2011 to the Defendant’s corporate bank account.
Therefore, the Defendant is obligated to pay damages for delay calculated at the rate of 15% per annum from April 26, 2016 to the date of full payment, as the Plaintiff seeks from the date following the delivery date of the application for the instant payment order, to the date of full payment, as the Plaintiff seeks.
2. It is so decided as per Disposition by the assent of all participating Justices, on the ground that the plaintiff's claim is reasonable.