logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 서울중앙지방법원 2014.06.19 2013가합47588 (1)
추심금
Text

1. The plaintiffs' claims against the defendants are all dismissed.

2. The costs of lawsuit are assessed against the plaintiffs.

Reasons

1. Basic facts

A. Defendant A as the Defendants is the owner of not less than 1,180§³ in Namyang-si, Namyang-si, and the owner of the said land-based multi-unit housing D Adong Construction Corporation (hereinafter “Adong Construction Corporation”), Defendant B is the owner of the said land-based multi-unit housing 14 households (hereinafter “Cdong Construction”) and the Defendant Company is the owner of not less than 2,015§³ in the said land-based multi-unit housing and the owner of the said land-based multi-unit housing 19 households in the said land-based multi-unit housing (hereinafter “Bdong Construction Corporation”).

B. A, B, and C, and the Defendants: (i) On September 2009, the Defendants are Boll Construction Co., Ltd. (hereinafter “Nuri Construction”) around September 2009.

A, B, and C Dong Corporation (hereinafter referred to as “instant construction”) on the ground, such as C, E, and F, Nam-si, Nam-si, the Defendants owned at that time.

On the other hand, the construction was contracted, and the construction was around that time, G Co., Ltd. (hereinafter “G”).

A and C & H Co., Ltd. (hereinafter “H”)

(2) On May 17, 2010, G and H subcontracted each part of the instant construction works to the Plaintiffs again. 2) The instant construction works commenced and continued on September 2009, and the Defendants concluded a construction contract with G and H to directly contract the instant construction works to G and H (hereinafter “instant contract”).

The main contents are as follows:

Contractor: G, H contractor: I, J, K

1. Construction name: New construction works in South-North Korea D (tentative name);

2. Construction place: F in the Namyang-si, and four parcels;

3. Date of the commencement of construction: The date of resumption of construction on May 17, 2010: September 30, 2010 (the first project owner Defendant Company, Defendant A case), October 30, 2010 (the second project owner Defendant B case).

4. Contract amount: 6,300,000 won.

6. The cost of construction after the completion of the construction project and its resumption shall be the excess of KRW 2.5 billion, operated and completed within the limit of KRW 2.5 billion, to which the Defendants can mobilize.

arrow