logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 수원지방법원 2018.06.20 2016가합73586
계약금 반환 등
Text

1. As to the Plaintiff’s KRW 120,00,000 and KRW 20,000 among them, Defendant D Co., Ltd. shall start on June 21, 2013, and 80.

Reasons

1. Basic facts

A. On March 12, 2013, between Defendant E, G He and Defendant D and Nonparty J, the Non-Party D and the Non-Party J entered into a business agreement related to the authorization and permission of the real estate is the owner of K, L, and the Defendant E is the owner of M, N,O, and P land. Defendant G is the owner of Q land (hereinafter collectively referred to as the “instant land”), Defendant E, G, and Non-Party D and Non-Party J entered into the pertinent agreement with Defendant D and Non-Party J on March 12, 2013, by carrying out design services necessary for the development project of the instant land, the maintenance of business following the completion of authorization and permission, and after selling the instant land after completion of authorization and permission, the sales of the said land and the settlement of the profits therefrom to Defendant D and Non-Party J on the basis of the agreement on the permission (hereinafter referred to as the “instant agreement”).

B. On June 21, 2013, Defendant D entered into an offer contract between Defendant D and the Plaintiffs; Defendant D entered into an offer contract with Plaintiff A and C; and on February 14, 2014, with Plaintiff B, respectively, with each of the following items: (a) written offer contract between the Plaintiff D and the Plaintiff (hereinafter “instant contract”).

(B) The main contents of each of the above contracts are as follows (as described below between the plaintiff C and the plaintiff).

1. Plaintiff A’s seat: K, L, N, and P (hereinafter the above four parcels, collectively referred to as “instant development project site”;

() Shares in a building: Shares in co-ownership of 199.17 square meters in a neighborhood living facility-1 story (30 square meters): The amount of co-ownership shares of KRW 360,000,000, and the amount of actual supply of KRW 180,000: The payment procedure for down payment of KRW 20,000,000 on June 21, 2013 (the contract date): The remainder of KRW 80,000,000 in an intermediate payment of KRW 20,000 on February 14, 2014 (the time of completion of authorization) and the remainder of KRW 80,000 on December 31, 2014 (the date of designation for entry).

2. Plaintiff B’s location: K, L, N, and P building shares in the wife population in Gyeonggi-do.

arrow