본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
(영문) 인천지방법원 2015.03.20 2014가합2576
대여금
Text
1. The Defendant shall pay to the Plaintiff KRW 230,00,000 as well as 20% per annum from November 29, 2014 to the date of full payment.
Reasons
1. Indication of claim;
A. On December 6, 2010, the Plaintiff lent KRW 230,000,00 to the Defendant. However, the Defendant did not repay the above loan until the maturity date.
B. Therefore, the Defendant is obligated to pay to the Plaintiff damages for delay at the rate of 20% per annum from November 29, 2014 to the day of full payment, which is the day following the delivery of the original copy of the instant payment order, to the day of the delivery of the original copy of the instant payment order.
2. Articles 208 (3) 1 and 257 of the Civil Procedure Act of the applicable provisions of Acts;