On September 20, 2019 and October 2, 2019, the defendant's corrective order against the plaintiff is revoked.
Reasons
1. Details of the disposition;
A. On March 2, 2018, the Plaintiff purchased a 376.76 square meters on the first floor of a warehouse of the general steel structure E-dong general steel structure, and 220.4 square meters on the first floor of a warehouse of the F-dong general steel structure (hereinafter referred to as the “D warehouse of this case”) from the Plaintiff on March 2, 2018, for a general steel structure and other roof warehouses (hereinafter referred to as the “instant warehouse”), 1,066 square meters on the land, and its ground E-dong general steel structure, and registered the ownership on March 29, 2018, each warehouse facility of the E-dong and F, the “D warehouse of this case” (hereinafter referred to as the “each warehouse of this case”). The Plaintiff purchased the “instant warehouse” and the “D warehouse of this case” of this case, and registered the ownership transfer on March 29, 2018.
B. On October 207, G, the first owner of the owner’s interest in each of the instant warehouses, entered the building report on the instant warehouse as “a warehouse facility (a farm store)” and obtained approval for use for the same purpose on December 2, 2007. As to the instant D warehouse, the first owner of each of the instant warehouses filed an application for permission for change of use with “a building report and plant-related facilities” as “a building report and approval for use,” and filed an application for permission for change of use with “a warehouse facility (a farm store)” on March 2012, 2012.
(c)
At the time of the Plaintiff’s purchase of each of the instant warehouses, the current status of the building ledger for each of the instant warehouses was indicated as “a farm warehouse” or “a factory (a farm store)”, and the building ledger was indicated as “a general steel structure warehouse (a warehouse)” or “a general steel structure warehouse (a warehouse).”
(d)
The Defendant issued a corrective order to the instant D warehouse on September 20, 2019 pursuant to Article 79(1) of the Building Act, on the ground that the Plaintiff violated Article 19 of the Building Act by altering the purpose of use from each of the instant windows to a general warehouse of a farm household without permission, and issued a corrective order to the instant warehouse as of October 2, 2019 (hereinafter “instant disposition”).