Text
1. The Defendant’s KRW 44,515,00 for the Plaintiff and KRW 5% per annum from April 18, 2015 to November 11, 2016.
Reasons
1. Basic facts
A. (1) The execution of the instant service contract, etc. (1) The said six companies below the above six companies, “solar power generation business operators,” both below the “solar power generation business operators,” in the case of the instant service contract, including the development of the instant service contract, in the case of the Gyeong-si, Chungcheongnam-si, Chungcheongnam-si, the K-si, the K-si, the K-si, the K-si, the K-si, the K-si, the K-si, the K-si, the
In relation to the construction of six solar power plants (hereinafter “instant construction”), the Plaintiff was awarded a contract for the instant construction from a solar power plant operator around 2012, but the instant construction was transferred to a third party.
(2) On October 27, 2014, the Plaintiff entered into a contract with the Defendant to provide the Defendant with technical services, etc. relating to the instant construction works, and the Defendant paid KRW 100,000,000 to the Plaintiff on the day when the Plaintiff entered into the said contract:
(hereinafter referred to as the “instant service contract”). The contracting parties to the technical service contract shall be Gap (Defendant), Eul (Plaintiff): The contract amount of two parcels (so-called "so-called solar power plant services-related contract amount of 46-1-2 parcels of Gyeongnam-do, Gyeongnam-do: one hundred million won per day (so-called 261,500,000 won): the service period-based contract amount of 27 October 2014: The contract amount of five hundred and sixty million won per day (so-called 261,50,000 won): the basic civil construction costs, the alteration of the design of civil works, the cost of building construction, the alteration of the village civil petition, the cost of relocation of trees, the cost of payment of expenses for removal of pine trees: Contract deposit - All billion won (so-called 200,000,000 won), the remainder of the value-added tax] - The scope of the service contract shall be separately set forth in Article 305,000,000 won per day.
Article 5 (Modification of Contract)
1.A change may be made through consultation between "A" and "B" if such change is necessary in the project plan during the performance of the task of this service.
2.A modification of the “A”’s project plan would be significantly different from the original work plan.