(영문) 광주지방법원순천지원 2016.10.13 2016가단10517
물품대금
Text

1. The Defendant shall pay to the Plaintiff KRW 36,312,00 and interest rate of KRW 15% per annum from July 16, 2016 to the day of complete payment.

Reasons

According to the overall purport of Gap evidence Nos. 1 and 2, the plaintiff supplied sand to the defendant from March 2015 to November 2015, 2015, but did not receive KRW 36,312,00 from the defendant, and the plaintiff prepared and issued a payment certificate for the above attempted money on March 29, 2016, but did not receive the above attempted money until the date of the closing of argument.

Therefore, the Defendant is liable to pay to the Plaintiff the amount of KRW 36,312,00 and damages for delay calculated at the rate of 15% per annum from July 16, 2016 to the day of complete payment, as the Plaintiff seeks, as the result of sand supply, from the date of delivery of the original copy of the instant payment order, to the day of full payment.

The plaintiff's claim is accepted.