Text
1. Of the judgment of the court of first instance, the part against the defendant exceeding the following amount ordered to be paid shall be revoked.
Reasons
1. The name of basic fact construction: The contract date of the new construction works and appurtenant construction works of the defendant factory, the date of commencement: the date of completion of the completion of the works on July 30, 2014: 1,540,000 won (including value-added tax) - Contract deposit: 100,000,000 won (payment on March 25, 2014) - Part payment: 1,070,000 won (payment on March 25, 2014): 370,000,000 won (payment at the completion of 70% of the steel frame construction) - Balance: 370,00,000 won (payment within 14 days after completion of the works);
A. On March 20, 2014, the Plaintiff (formerly: C Co., Ltd.) contracted from the Defendant for the construction of the Defendant’s factory (hereinafter “instant factory”) on the ground that it was located on the grounds that it was located on the ground that it was located on, and that the content of the contract is as follows.
(hereinafter “instant construction contract”). B.
On May 28, 2014, the Plaintiff and the Defendant agreed to partly modify the terms and conditions of the instant construction contract (excluding the reduction of construction, additional construction) and agreed on the settlement of construction cost and modification of design, as follows:
(4) Partial modifications of the above construction work are "the modification of the construction of this case", combined with the above agreement and agreement, and hereinafter referred to as "the present construction alteration agreement"). Part 1 of the Exclusion (Reduction) Additional Construction Part 1) Factory Jdong office, president office, warehouse, toilet 2) Factory Jdong office, president office, and warehouse 3) Factory-dong floor concrete thickness (T=300 T=200) factory floor height (T=300 T=300) factory floor height (250 6) civil engineering packing work (250 m30 m), part of the outer parking lot floor (a concrete) construction (excluding mix concrete) construction (excluding part 10 outside mplate building) construction) construction of the Kadong-dong floor extension (excluding part 10 outside mplate building) construction, extension of 1020 Dong-dong office, 36,250 dong-dong office, and extension of the construction of the building site (excluding 360 mpump site) construction).