Text
1. The defendant shall pay to the plaintiff KRW 31,188,143 and KRW 29,744,056 among them, from August 26, 2014 to the day of full payment.
Reasons
1. Since the facts stated in paragraphs (1) through (3) of the attached Form of the claim as to the cause of the claim do not dispute between the parties, the Defendant is obligated to pay to the Plaintiff damages for delay calculated at the rate of 18% per annum from August 26, 2014 to the date of full payment of the principal amount of two principal and interest as of August 25, 2014 and 29,744,056 won, which is the sum of principal and interest of two principal and interest of the Plaintiff as of August 25, 2014.
2. The defendant's assertion argues that the defendant cannot respond to the plaintiff's claim since he applied for individual rehabilitation. However, even if the individual rehabilitation procedure against the defendant begins, it is permitted to suspend or prohibit the act of receiving repayment of individual rehabilitation claims or demanding repayment. Thus, the claim sought by the plaintiff in the lawsuit in this case was confirmed as individual rehabilitation claims by the closing date of argument in this case.
Unless there is any assertion as to the fact that there was a decision to authorize the repayment plan or that there was a decision to authorize the repayment plan, the defendant cannot refuse the plaintiff's claim. Therefore, the defendant'
(3) Therefore, the claim of this case shall be accepted in conclusion, even if the judgment of this case became final and conclusive.