(영문) 서울동부지방법원 2015.11.18 2015가단100106
양수금
Text

1. The defendant shall pay the plaintiff KRW 130,000,000.

2. The plaintiff's remaining claims are dismissed.

3. Of the costs of lawsuit.

Reasons

In addition to the statement in Gap evidence Nos. 1 through 4, the defendant performed a loan (hereinafter "the loan of this case") on January 16, 2001 with a limit of 50 million won on loan and due date set on January 16, 2002 to Co., Ltd. of the 21st century as of January 16, 200, and the defendant jointly guaranteed the above loan obligations with a limit of 65 million won. The bank of Korea and the 21st century Detailed Co., Ltd. of the 201st century increased the loan amount of 50 million won on February 10, 201, the defendant also increased the guarantee limit amount of the loan of this case to 65 million won, the claim of this case was transferred in sequence and finally transferred by the plaintiff on April 28, 201, and the transferor of this case notified the transfer of the loan of the fact in succession to the Co., Ltd. of the loan of this case on May 16, 2015.

According to the above facts, the defendant is obligated to pay KRW 130 million to the plaintiff as a joint and several surety for the debt of this case. Thus, the plaintiff's claim is justified within the extent of the above recognition, and the remainder is dismissed as it is without merit. It is so decided as per Disposition.

arrow