logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 인천지방법원부천지원 2016.06.15 2015가합103820
건물명도
Text

1. The defendant shall collect each obstacle in attached Nos. 1 through 73 from the plaintiff, and the same list Nos. 74 through 73.

Reasons

1. Facts of recognition;

A. B Project implementation and expropriation ruling of land, etc. 1) Kimpo-market and C Co., Ltd. (hereinafter “C”).

In order to jointly implement B, the Gyeonggi-do Governor approved an industrial complex plan pursuant to Article 15(1) of the Act on Special Cases concerning the Simplification of Authorization and Permission Procedures for Industrial Complexes, and the Gyeonggi-do Governor applied for adjudication to the Gyeonggi-do Local Land Expropriation Committee as the Gyeonggi-do Public Notice D (F ( September 8, 2013), Gyeonggi-do Public Notice E ( September 10, 2013), Gyeonggi-do Public Notice F (F ( June 5, 2014), Gyeonggi-do Public Notice G ( July 17, 2014).

Accordingly, on August 31, 2015, the Gyeonggi-do Regional Land Tribunal accepted the land, etc. listed in [Attachment 1] No. 1 and No. 2 (hereinafter “instant land”) owned by the Defendant for the said project, and transferred the buildings listed in [Attachment 1] No. 3 (hereinafter “instant building”) and the obstacles listed in [Attachment 2] List No. 1] owned by the Defendant (hereinafter “instant obstacles”), and the compensation for losses shall be KRW 1,274,88,350 for H, and KRW 530,835,750 for the Defendant, and the commencement date of expropriation (transfer) shall be October 15, 2015.

3) According to the above ruling of expropriation, C paid KRW 1,274,88,350 to H on October 14, 2015, and deposited KRW 530,835,750 to the Defendant. B. Pursuant to Article 45 of the Act on Acquisition of and Compensation for Land, etc. for Public Works, etc. for the instant land and the instant building, the Plaintiff, who acquired the Plaintiff’s ownership as to the instant building, and the Kimpo Market and C, are the project implementer that acquired the Plaintiff’s ownership as to the instant land and the instant building, and completed the registration of ownership transfer on November 18, 2015 for the instant land and the instant building, and on the same day, C respectively entrusted the instant land and the instant building to the Plaintiff.

arrow