logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 서울서부지방법원 2015.10.29 2014가합39381
공사대금
Text

1. The plaintiff's claim is dismissed.

2. The costs of lawsuit shall be borne by the Plaintiff.

Reasons

(b)in the construction work to take out the residues and to transport it to a sand site;

The term “stoptop” was determined from April 1, 2012 to August 30, 2013 as the agreed amount of KRW 1,970,759,610 to the construction period and accepted the subcontract (hereinafter “instant subcontract”) and “the instant subcontracted work”.

(2) The main contents of the instant subcontract are as follows: (a) the agreement to participate in the execution of the instant case (hereinafter “instant agreement to participate in the execution”).

(1) Article 2(1) of the Agreement on Participation in Construction - Article 2(1) of the said Agreement provides that the Plaintiff shall undertake and participate in the construction of the remaining soil treatment work within the construction period from among the earth and sand works in the first stage of the D market facility modernization project. Article 3(1) of the said Agreement provides that the period of the agreement shall be from April 1, 2012 to August 30, 2013 (the scope and content of the construction) - Pharmatom weather - Pharmatom, residual soil treatment (c) - Pharmamtom, residual soil treatment (c) - Pharmamtom, residual soil treatment (c) - Pharmamtom, residual soil treatment (c) - The amount of the agreement shall be calculated without any changes in the unit price for the retirement benefit from the Sungnam Seoul International Airport (Do 7.6 km) to the date of the completion or change of the construction work.

② The above agreed amount is the amount determined by mutual consultation according to the Defendant’s execution drawings and construction specifications and the result of sufficient review of specifications, and the unit price determined by the time the participation in construction is completed, and there is no increase in unit price

(3) The defendant shall verify the amount of progress payment each month in actual construction and observe the payment conditions of the project owner.

arrow