logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 대구지방법원 2017.08.11 2015가합200870
공사대금
Text

1. As to KRW 60,484,870 and KRW 50,484,870 among the Plaintiff, Defendant A shall be from January 3, 2015 to August 11, 2017.

Reasons

1. Basic facts

A. On July 2014, the Defendant entered into a contract with Defendant B, C (hereinafter referred to as “C”), and D (hereinafter referred to as “D”), under which the said companies contracted to the Defendant to install each solar power plant (the remainder is different from the display part and the remainder is the same) as follows:

(hereinafter, the contract between the defendant and the defendant B is referred to as "the original contract of this case") as a standard contract for private construction works.

1. Syms: Installation works for solar power plants (two balls);

2. The construction site: The E and seven parcels (Defendant B) , Chungcheongnam-gun, Chungcheongnam-gun, Chungcheongnam-gun, and the F, and four parcels (C), other than the 10 parcels (D), Chungcheongnam-gun, Chungcheongnam-gun, Chungcheongnam-gun, and the 10 parcels (D).

3. Date of arrival: The scheduled date for completion of works on July 4, 2014: 726,000,000 won in total for three power plants on October 35, 2014 (including each 242,00,000,000 won, value-added tax);

8. Payment item of materials: Defendants B, representatives, and contractors of all materials, such as servers, water distribution team, connection team, boiler cable container, steel bars, fracks, structures, and fracks: H C, representatives: ID, representatives: K, representatives: A special agreement entered into by Defendant A.

1.The contractor shall pay the materials necessary for this project.

2.The contractor shall assist the contractor with the working equipment, tools and technical personnel required for this project.

3.The contractor must pay off the site of materials necessary for this project.

9. In the event of a problem (such as fluor, fluor, decline in the volume of power generation, fluoring, damage, etc.) on the foundation and facilities of a solar power plant, the contractor shall promptly supplement the situation;

B. Around July 25, 2014, the Plaintiff entered into a contract with the Defendant to contract the Plaintiff with the basic construction, structure assembly, and rupture assembly construction, etc. (hereinafter “instant construction”) of the 6folds of installation works for solar power plants with the following content:

(hereinafter referred to as “instant subcontract”). Standard contract agreement for private construction works

1. Sags: 6 metropos to install solar power plants;

2. Place of construction:

arrow