Text
1. As to KRW 605,939,384 and KRW 605,00,00 among the Plaintiff, the Defendant shall pay to the Plaintiff KRW 605,939,384 from October 11, 2014 to November 5, 2015.
Reasons
1. Basic facts
A. The Plaintiff and the Defendant’s construction contract 1) The Defendant concluded a construction contract with the Plaintiff and the Defendant, at Jeju, “D” with the size of the first and third floors above ground, which are accommodation facilities in C (hereinafter “instant cartel”).
(2) In order to remodel and extend the instant cartels around June 2013 while operating the instant cartels, the remodeling and extension work for the instant cartels to F, one’s husband and representative director, who are the husband of Nonparty E and the Plaintiff’s representative director (hereinafter “instant construction”).
2) The Plaintiff and the Defendant drafted a total of three construction contracts (Evidence No. 1 and No. 1 and No. 2) relating to the instant construction works as follows. Of them, one of the construction contracts (Evidence No. 1) was prepared by making the contractor’s name a non-party comprehensive construction company (hereinafter “former comprehensive construction company”).
(A) Standard contract for private construction works
1. Name of the project: Remodelling and extension works for the Jeju G accommodation facilities;
2. The place of construction: Jeju.
3. Date of commencement: January 17, 2014.
4. Date scheduled for completion: May 30, 2014.
5. Contract amount: Amount of 1,375,00,000 won per day (including value-added tax): Amount of 1,375,000 won per day, value-added tax per day, the amount of 125,00,000 won per day); Interest rate of delay in payment: 8% per year for a contract for a standard construction contract for a private construction project; and
1. Name of the project: Remodelling and extension works for the Jeju G accommodation facilities;
2. The place of construction: Jeju.
3. Date of commencement: January 17, 2014.
4. Date scheduled for completion: March 30, 2014.
5. Contract amount: daily wage of KRW 966,900,000 (including value-added tax): KRW 208,320,501 daily wage, value-added tax of KRW 87,900,000; and
1. Name of the project: Remodelling and extension works for the Jeju G accommodation facilities;
2. The place of construction: Jeju.
3. Date of commencement: April 28, 2013.