logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 서울중앙지방법원 2016.07.26 2015가단148839
손해배상(기)
Text

1. The plaintiff's claim is dismissed.

2. The costs of lawsuit shall be borne by the Plaintiff.

Reasons

(b) the facts of the basis;

A. On June 21, 2010, the Plaintiff concluded a construction contract with the Defendant on the condition that the construction cost shall be KRW 699,160,000 (including value added tax) and the rate of liquidated damages shall be 2/1000 per day with respect to the construction work for the individual heating conversion and replacement of water supply pipes of the new and new large apartment, and agreed on the construction period as follows.

According to the site descriptions attached to the instant construction contract, the site descriptions include “gas boiler installation (integrated with gas boiler and pipeline construction) of the gas boiler in the control room,” and “including the installation (capacity) of two high temperature water control machines at the elderly time, as soon as possible.”

4. 공사기간 : 착공 2010. 7. (샘플세대 승인일 이후부터) 준공 2010. 9. 20. * 세대내 개별보일러 공사와 가스공용라인공사는 추석 전까지 완성하며 단 장기부재세대, 공사거부세대(10% 범위)는 준공에서 제외한다

(Date Date for Completion: September 20, 2010) * Water-supply pipes replacement Corporation shall be until October 30, 2010 after conversion of individual heating to each household.

Provided, That the construction of water supply pipes shall be commenced within one month after the commencement of development heating.

B. On October 29, 2010, the Plaintiff and the Defendant entered into a contract for each additional construction work with the construction cost of KRW 6,545,000 (including value-added tax) for the fire hydrant relocation work, from October 29, 2010 to November 30, 2010, with the construction period of KRW 26,004,00 (including value-added tax) for the replacement work within the Shesheet Sheet Sheet Sheet Sheet Sheet, and with the construction period of November 29, 2010 to November 18, 2010. The written contract for the additional construction is stipulated as follows special articles:

* 특기사항 1) 본 공사(개별난방 및 급수배관공사)는 급수배관(추가부분 포함) 종료시점인 11월 18일을 준공으로 한다. 2) 본 공사에 대한 A/S는 11월 30일로 종료한다

(A/S generation may be adjusted in addition to A/S generation) The completion documents for the entire project shall be submitted on November 18, 198. (4) The completion inspection will take place on November 20.

C. The Defendant on November 18, 2010.

The main construction works and b.

(b).

arrow