(영문) 제주지방법원 2017.04.25 2016가단17292
공사대금
Text

1. The Defendant shall pay to the Plaintiff KRW 40,00,000 and the interest rate of KRW 15% per annum from January 17, 2017 to the day of complete payment.

Reasons

1. Claim for the payment of the construction cost due to the completion of construction works by a subcontract for construction works, such as mold, cryp construction, removal, steel processing, assembling, etc. among the new construction works of the C commercial building in Seopoposi City from the Defendant;

2. Judgment without holding any pleadings (Article 208 (3) 1 of the Civil Procedure Act);

arrow