(영문) 창원지방법원 밀양지원 2015.03.12 2014고단368
국토의계획및이용에관한법률위반등
Text

Defendant shall be punished by a fine of KRW 8,000,000.

If the defendant does not pay the above fine, 100,000 won shall be one day.

Reasons

Punishment of the crime

1. Any person who intends to engage in the activities in violation of the National Land Planning and Utilization Act and the Farmland Act shall obtain permission for development activities, and obtain permission for farmland diversion in order to divert farmland in an agricultural promotion area, and shall not engage in any land utilization activity that is not directly related to the production of agriculture or the improvement of farmland in an

Nevertheless, on May 2014, the Defendant did not obtain permission for development and farmland diversion, and performed flat work, such as land suspension work, in order to build a c, D, and a total of 1,208 square meters in an agricultural and forest area and an agricultural promotion area, in order to build a c, D, and a total of 1,208 square meters; performed development activities without permission by breaking c, diverting c, and diverting c, diverting farmland; and conducted land use activities not directly related to agricultural production or farmland improvement in

2. Any person who intends to occupy and use land in a river area shall obtain permission from the river management agency.

Nevertheless, the Defendant did not obtain permission from the river management agency, from November 20, 2012 to the present date, occupied the river area without permission by installing four steel tent facilities and 32 square meters in the area equivalent to approximately 900 square meters in the river area in Seoyang-si, Seoyang-si, and constructing a shower room building.

3. Any person who intends to construct a building with a total floor area of less than 200 square meters and less than three floors in a management area under the National Land Planning and Utilization Act in violation of the Building Act shall report to the competent authority

Nevertheless, on September 2013, the Defendant constructed a shower room building with a size of 9 square meters from E in Syang-si in the preservation management area without filing a construction report.

Summary of Evidence

1. Defendant's legal statement;

1. A protocol concerning the suspect examination of the accused;

1. Each report on investigation;

1. Written investigation of illegal activities in the land cadastre, stopping ground, and prosecution joint control report, full certificate of registered matters, and NA.